CIP-014-3 1.1—CIP-014-3 1.1
>Control Description
Subsequent risk assessments shall be performed:
• At least once every 30 calendar months for a Transmission Owner that has identified in its previous risk assessment (as verified according to
Requirement R2) one or more Transmission stations or Transmission
substations that if rendered inoperable or damaged could result in instability, uncontrolled separation, or Cascading within an Interconnection; or
• At least once every 60 calendar months for a Transmission Owner that has not identified in its previous risk assessment (as verified according to
Requirement R2) any Transmission stations or Transmission substations that if rendered inoperable or damaged could result in instability, uncontrolled separation, or Cascading within an Interconnection.